Development permit
Town of Cochrane Planning Services
Most development in Cochrane needs a development permit, including constructing new buildings and adding to existing ones. Industrial and commercial projects use the Town's non-residential application package, emailed to Planning Services. The Development Officer or the Cochrane Planning Commission decides within 40 days of a complete application, and the Town says the whole process takes a minimum of 10 to 12 weeks including the three-week appeal period. Development must start within 1 year of the permit's release and be completed within 2 years unless the conditions say otherwise.
Source: Development Permits & Telecommunication Towers | Town of Cochrane